Earthwork & observed-cycle output

Wheel Loader Productivity Calculator

Relate loose bucket load, observed active cycle and a separate delay allowance to hourly output.

177 / WHEEL LOADER PRODUCTIVITY

Your numbers.
A clearer decision.

Free to use. No signup.
Inputs stay in this browser.

Starting values are illustrative. Use your own costs, rates and assumptions.

INPUT GROUP 01

Entered assumptions and matching units

YOUR CALCULATION

Estimate loader output from entered bucket volume and observed cycle time.

Loose-state volume per cycle (m³)

2.7

Effective loose volume per hour (m³/h)

259.2

Mass at entered loose bulk density (t/h)

414.72

Keep the calculation

Saving is optional and stays on this device. Unsaved edits are not kept when you leave. CSV includes every input and the current results.

Illustrative inputs loaded. Replace them with your own assumptions.

How the wheel loader productivity calculator works

Volume per cycle equals bucket volume times fill fraction. Cycles per hour equal 60 divided by active cycle minutes. Multiply by one operating-efficiency factor for delays excluded from that active cycle.

Same-state loose bulk density converts loose volume per hour to metric tonnes per hour. Do not apply a delay factor already reflected in the observed cycle.

This is output arithmetic, not rated payload, tipping load, lift capacity, bucket suitability, travel safety or a guarantee of site productivity. Enter observed, qualified parameters rather than treating the defaults as machine settings.

Worked example

A 3-m³ bucket at 90% fill carries 2.7 loose m³. At a 0.5-minute active cycle and 80% operating efficiency, output is 259.2 m³/h or 414.72 t/h at 1.6 t/m³. A one-minute cycle yields 129.6 m³/h.

Sources and assumptions

The source material explains the underlying calculation or pricing structure. Entered prices, costs, schedules and scenario choices are your assumptions; this tool does not obtain supplier quotes or predict actual results.

Calculation methods, testing and sources · Practical calculation guides