Earthwork & operating budgets

Earthmoving Cost per Unit Calculator

Allocate productive and standby costs to output in one matched material state.

160 / EARTHMOVING COST PER UNIT

Your numbers.
A clearer decision.

Free to use. No signup.
Inputs stay in this browser.

Starting values are illustrative. Use your own costs, rates and assumptions.

INPUT GROUP 01

Entered assumptions and matching units

YOUR CALCULATION

Allocate operating and standby costs to the entered material output.

Operating plus standby cost

$1,120.00

Produced volume in the declared state (m³)

600

Mass at the same-state bulk density (t)

960

Cost per produced m³

$1.87

Cost per produced metric tonne

$1.17

Keep the calculation

Saving is optional and stays on this device. Unsaved edits are not kept when you leave. CSV includes every input and the current results.

Illustrative inputs loaded. Replace them with your own assumptions.

How the earthmoving cost per unit calculator works

Produced volume is productive hours times production per productive hour. Produced mass multiplies volume by the entered bulk density. Total period cost adds productive and standby hours at their separate combined cost rates.

Divide period cost by output for cost per m³ or per metric tonne. Zero output leaves a unit-cost ratio unavailable while retaining incurred period cost; standby adds cost without output.

Volume and density must both use the same bank, loose or compacted basis. No swell, compaction, payload legality or machine rating is inferred. Include the same crew and machine cost components in each entered hourly allowance.

Worked example

Six productive hours at $150 plus two standby hours at $110 cost $1,120. Output at 100 m³/productive hour is 600 m³ or 960 t at 1.6 t/m³. With no standby, total cost is $900.

Sources and assumptions

The source material explains the underlying calculation or pricing structure. Entered prices, costs, schedules and scenario choices are your assumptions; this tool does not obtain supplier quotes or predict actual results.