Earthwork Swell & Shrink Calculator

Apply separately entered bank-to-loose and bank-to-compacted factors, with a density-based mass perspective.

102 / COMPARE BANK, LOOSE AND COMPACTED

Your numbers.
A clearer decision.

Free to use. No signup.
Inputs stay in this browser.

Starting values are illustrative. Use your own costs, rates and assumptions.

INPUT GROUP 01

Same material and dry-mass basis

YOUR CALCULATION

Keep bank, loose and compacted quantities on explicit reference bases.

Loose volume · m³

125

Compacted volume · m³

90

Assumed conserved dry mass · tonnes

180

Implied loose dry density · tonnes/m³

1.44

Implied compacted dry density · tonnes/m³

2

Keep the calculation

Saving is optional and stays on this device. Unsaved edits are not kept when you leave. CSV includes every input and the current results.

Illustrative inputs loaded. Replace them with your own assumptions.

How the earthwork swell & shrink calculator works

Both volume changes refer to the original bank volume. Loose volume = bank volume × (1 + loose increase / 100). Compacted volume = bank volume × (1 − compacted reduction / 100). The compacted reduction must be below 100%; it is not a reduction from loose volume.

Conserved dry mass = bank volume × entered bank dry density. Implied loose and compacted dry densities divide that mass by the respective calculated volumes. At zero bank volume, mass and volumes are zero and the density ratios are unavailable.

This scenario assumes no imported material, removed fines, water mass change or loss. Factors depend on actual material and conditions. The results do not prescribe target density, compaction effort, test acceptance, safe slopes or hauling limits. Caterpillar discusses bank/loose conventions; these explicit forward factors avoid relying on ambiguous inverse load-factor terminology.

Worked example

100 m³ bank volume with 25% loose increase becomes 125 m³ loose. A separate 10% reduction from bank gives 90 m³ compacted. At 1.8 tonnes/m³ bank dry density, conserved mass is 180 tonnes. Implied loose density is 1.44 tonnes/m³ and compacted density is 2. Changing loose increase to 50% gives 150 m³ loose and 1.2 tonnes/m³ implied loose density.